Project Administration
Amendments or Modifications to Subcontracts
To request a change in a subcontract, the principal investigator must submit a new "Request for Subcontract" form (PR-033) to the sponsored program officer asking for an amendment to the subcontract. The sponsored program officer will prepare the amendment and obtain all necessary approvals and signatures. The sponsored program officer will then forward the "Request for Subcontract" and the amendment to Procurement. Competitive bidding requirements based on the aggregate total of the subcontract, if applicable, must also be met. Procurement will then issue a change order in accordance with the approved amendment.